From John Ray's shorter notes




September 08, 2021

Queensland water utility wins appeal against 2011 flood damages ruling

The Wivenhoe dam could easily have stopped the flood but it was mismanaged by the bureaucrats in charge of it  -- who ignored their own manual.

This judgment says that the operators can do what they want as long as they agree with one-another!  This should go to the High Court


State-owned dam operator Seqwater has won an appeal against a landmark ruling on the 2011 Queensland floods.

In 2019, the Supreme Court in New South Wales found the Queensland government, Sunwater and Seqwater, had acted negligently and had contributed to the disaster.

It was ruled engineers had failed to follow their own flood mitigation manual, leading them to release large volumes of water at the height of the flood, damaging more properties.

A judge ordered more than 6,500 victims whose homes or businesses were damaged were entitled to almost $900 million in compensation.

Two of the defendants agreed to pay their share of the settlement but Seqwater — which was found liable for 50 per cent — appealed against the decision on a number of grounds.

During a hearing in May, Seqwater argued engineers had acted appropriately and the decisions about water releases were suitable.

In a published judgment today, three NSW Court of Appeal judges ruled the engineers "acted by way of consensus" and "ultimately" followed the strategy determined by the senior flood operations engineer and were not in breach of the Civil Liability Act.

"Failure by Seqwater's flood engineers to depart from that strategy was not proven to be in breach," the judges found.

"Even if their conduct departed from the manual, that did not of itself entail a breach of that standard."

Ipswich councillor and Goodna flood victim Paul Tully slammed the unexpected decision as a "kick in the guts" to many still-struggling flood victims.

"This decision defies commonsense and logic given that SunWater and the state government have already accepted they were jointly liable for the flood," Mr Tully said.

"We now have the bizarre situation where the state government and SunWater have agreed to pay $440 million as their assessed 50 per cent liability, while Seqwater has squirmed out of its responsibility on a legal technicality."

Mr Tully accused Seqwater of legal delaying tactics over 10 years "lacking one iota of justice, common decency or fair play".

"In the past decade, many flood victims have passed away, marriages have failed and people have suffered mental breakdowns as a result of the legal delays."

The judgment also rejected the initial judge's determination that losses had been caused by the "cumulative effect" of several breaches by the flood engineers.

"That approach was artificial … and assumed that each flood engineer could and should exercise independent judgment," the judges found. "The flood engineers acted in a collaborative manner … all were liable for each breach. "The fact that a particular engineer was on duty at a particular time was not a critical factor."

The matter was dismissed and the respondent was ordered to pay costs.

https://www.abc.net.au/news/2021-09-08/qld-court-2011-floods-appeal-hearing-class-action/100143440



This note originated as a blog post. For more blog postings from me, see
DISSECTING LEFTISM,
TONGUE-TIED,
EDUCATION WATCH INTERNATIONAL,
GREENIE WATCH,
POLITICAL CORRECTNESS WATCH, and
AUSTRALIAN POLITICS. I update those frequently.



Much less often, I update Paralipomena , A Coral reef compendium and an IQ compendium. I also put up occasional updates on my Personal blog and most days I gather together my most substantial current writings on THE PSYCHOLOGIST.



Email me here (Hotmail address). My Home Pages are here (Academic) or here (Personal). My annual picture page is here; Home page supplement; Menu of longer writings